Post-Storm Health Hut Infrastructure Repair
Project Launch: 3-3-17
The health hut in Temey Lewa World Connect previously supported was severely damaged by a storm system that affected the region in fall 2016. The roof of the structure has collapsed, the exterior wall has been racked by winds and water, and the hut is now non-operational. This project seeks to make repairs to the health hut so it can once again serve the people of Temey Lewa.
Project Update: 3-16-17
The mason made the bricks and the carpenter built the doors, completing them within four days. Currently, the mason has begun work on installing the bricks to repair the wall. During construction, the health hut has not been open for business, but it will reopen immediately after completion.